Horizontal Stabilizer – Day 23 – 2 hours

Well today was a glorious day on the project. I finished* the first major sub-assembly of my plane. The horizontal stabilizer is done. Only had one issue which required I drill out 2 rivets and that was with the elevator brackets getting in the way of the squeezer on some rivets. I just got out the…

November 26, 2013 in Empennage, Horizontal Stabilizer.

Horizontal Stabilizer – Day 22 – 3 hours

More riveting today. Finished up all the “bucked” rivets on the left side and moved onto the right. As I went, I found that putting a little masking tape over the mushroom set on the rivet gun reduces the marring on the skin. I saw this on some other builder sites. I’m planning on painting…

November 25, 2013 in Empennage, Horizontal Stabilizer.

Horizontal Stabilizer – Day 21 – 3 Hours

Today, I took a nice flight out to practice some short and soft field takeoffs and landings with my friend John and then I got started on the riveting. Here is the first bucked rivet of the project. Up to this point I’ve been able to “squeeze” the rivets. This is a little intimidating at…

November 24, 2013 in Empennage, Horizontal Stabilizer.

Horizontal Stabilizer – Day 20 – 1 Hour

Had a little time today so I riveted the front spar assembly together. Now it’s time to get the skins on.

November 19, 2013 in Empennage, Horizontal Stabilizer.

Horizontal Stabilizer – Day 19 – 2 Hours

A very exciting day. Spent about an hour priming. Got the hang of it pretty quickly. I have seen a bunch of people make a painting frame out of 2 x 4s and chicken wire. I’m definitely going to build one of these in the future. I used a plastic covered 4 x 8 sheet…

November 18, 2013 in Empennage, Horizontal Stabilizer.

Horizontal Stabilizer – Day 18 – 2 Hours

Today was pretty uneventful. I thought I would get some priming done but had a few errands come up. I got all the internal parts cleaned and they are all ready to be primed tomorrow. To prep, I “scrubbed” all the parts with water and a Scotch-Brite pad. Dried them and then went over them…

November 17, 2013 in Empennage, Horizontal Stabilizer.

Horizontal Stabilizer – Day 17 – 4 Hours

Today was a great day of progress on the plane. I finished de-burring the holes in the skins and dimpled the skins. I had a little time left so I de-burred the edges of the spar and skins as well. I’m so close to being able to rivet it all together. Tomorrow, I will, hopefully, get all…

November 16, 2013 in Empennage, Horizontal Stabilizer.

Horizontal Stabilizer – Day 16 – 2.5 Hours

Today, I finished up de-burring the holes in the skeleton and decided to start dimpling. Dimpling accomplishes the same thing as counter sinking except instead of cutting, we bend. So of course we use this process for thinner metal. I finished dimpling the skeleton today. I just have to de-burr and dimple the skins, de-burr all the edges…

November 13, 2013 in Empennage, Horizontal Stabilizer.

Horizontal Stabilizer – Day 15 – 1 Hour

Started de-burring all the holes in the skeleton. This is, pretty much, the most boring part of this project, but, absolutely necessary. After drilling, the holes have sharp edges that must be smoothed (Picture how easy aluminum foil is to rip…now imagine there’s an edge around a hole that thin. Cracks are most likely to…

November 12, 2013 in Empennage, Horizontal Stabilizer.

Horizontal Stabilizer – Day 14 – 2.5 Hours

Today I match drilled all the ribs to the new front spar for the left side, then attached the skin, match drilled the skin to the replacement front spar and match drilled the new rib. At this point, I am where I screwed up the left side before. Let’s see if I can successfully drill…

November 10, 2013 in Empennage, Horizontal Stabilizer.

Post navigation

← Older posts

Recent Posts

  • Elevator – Day 20 – 1 hour
  • Elevator – Day 19 – 4 hours
  • Elevator – Day 18 – 2.5 hours
  • Elevator – Day 17 – 4 hours
  • Elevator – Day 16 – 2 hours

Recent Comments

Elevator – Day… on Horizontal Stabilizer –…
Dave's avatarDave on Wings Arrived Today

Archives

  • June 2015
  • February 2015
  • September 2014
  • July 2014
  • June 2014
  • May 2014
  • April 2014
  • March 2014
  • February 2014
  • January 2014
  • December 2013
  • November 2013
  • October 2013
  • September 2013
  • October 2012

Posts by Project Phase

Meta

  • Create account
  • Log in
  • Entries feed
  • Comments feed
  • WordPress.com

Other Builders

  • Bruce Swayze's RV-7A Project
  • Jason Hess's RV-7A
  • Mike Bullock's RV-7

Builder Resources

  • Van's Air Force
  • Van's Aircraft
Create a free website or blog at WordPress.com.
Ryan Van Liere's RV-7A Project Page
Create a free website or blog at WordPress.com.
Privacy & Cookies: This site uses cookies. By continuing to use this website, you agree to their use.
To find out more, including how to control cookies, see here: Cookie Policy
  • Subscribe Subscribed
    • Ryan Van Liere's RV-7A Project Page
    • Already have a WordPress.com account? Log in now.
    • Ryan Van Liere's RV-7A Project Page
    • Subscribe Subscribed
    • Sign up
    • Log in
    • Report this content
    • View site in Reader
    • Manage subscriptions
    • Collapse this bar
 

Loading Comments...