Wings Arrived Today
ABF called yesterday to say the wings were at their warehouse and ask when to deliver them. Today, they have arrived. Guess I better get back to building. Still have the rest of the elevators to finish.
ABF called yesterday to say the wings were at their warehouse and ask when to deliver them. Today, they have arrived. Guess I better get back to building. Still have the rest of the elevators to finish.
Today, I built a bending brake out of a 2×8 and some hinges and put the final bends in the trailing edges. It was a pretty uneventful process. I had to push a lot harder than I though I would. The Brake: The goal is to have no taper in the bend prior to the…
I managed to get all the stiffeners and trim servo access panel/stiffener riveted onto the left skin. The aft most rivets were a pain. You can get to them with the rivet gun, but you really need 3 hands. One extra to peel the skin back. I clamped the skin to the table, put both…
Finally, got back to work on the project today after a brief hiatus. Today, Leza and I dimpled the elevator skins.
No work on the plane, but I did order the wings.
Wrapped up the rudder today (except the fiberglass tips and bearings to connect to Vertical Stab). All that was left today was to roll leading edge skins. This was done by taking a 5′ steel 3/4″ pipe and duct taping it along the edge and rolling it. A lot of force is applied down and…
I have reached the point where I totally screwed up rudder #1. I’m determined to do this right. Riveted trailing edge today. Took my time a lot more. Went very slow and checked straightness constantly. The result, a very straight trailing edge and no cracked rivets. Van’s gives a tolerance of 0.1″ deviation from straight.…
No pictures today on account of my hands being covered in sealant. Sealed trailing edge today. Now we play the waiting game.
Riveted the rudder skins on today…with the exception of the trailing edge.
I had a nice busy day in the shop today. I riveted on the counterbalance skin and rib, installed the counterbalance, countersunk the trailing edge, clecoed the skins on, and riveted on the top rib. The counterbalance all prepped and ready. Got all the rivets with a squeezer thanks to my new thin nosed 4″…